PERT is a method of analyzing the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project.
https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique

Question:

What are PERT and CPM?

Options:
A) Aids to decision maker
B) Decision making technique
C) Techniques to determine project status
D) All of the above
Solution:
Ans: (c) PERT(Programme evaluation review technique) and CPM(Critical path method) evaluates the project completion status.