Ram and Pasha can complete a job in 24 days. If Ram’s efficiency decreased by 66 and 2/3 % and Pasha’s efficiency is halved, the time in which they complete it can be ____.

(A) 45 days

(B) 75 days

(C) Either (A) or (B)

(D) Neither (A) nor (B)

Knowledge Expert

· commented

· 1 Months ago

@komal can u explain?

komal

· commented

· 1 Months ago

C